The Working Unit Kicevo – Ohrid is established by the decision of the Management Board of Victoria InVest in May 2015, in order to construct the Motorway Kicevo – Ohrid,

According to the Contract for construction of the Motorway:
– Victoria Invest International . is nominated subcontractor;
– Sinohydro Corporation Limited is Main Contractor
– Consorcium GIM, Euroconsulting and Geing Krebs und Kiefer is Engineer;
– Public Enterprise for state roads is Employer.

The total price of the Contract for construction of the Motorway Kicevo – Ohrid, section Kicevo – Podvis is 117.609.360,15 euro.
Reinforced concrete works of the Motorway participate with more than 60% in the total price of the Contract for construction of the Motorway.

The time period for completion is 38 months from the commencement date.

 

 

Contract Length Realization Reference Year of accomplish Contracting
Construction of Kicevo-Ohrid Motorway Package 5 & 6 (km33 + 740 up to 56+600)  23km 15 N/A ongoing Public Enterprise for State Road